Choosing a charger by how long people park

The most reliable way to pick a charger is not the vehicle type or the budget. It is the dwell time - how long a vehicle actually sits at your site.

When a site owner asks which charger they should install, the question usually arrives framed around power. Is 7 kW enough? Should we go straight to 22?

Power is the wrong place to start. Start with how long the vehicle is there.

Match the charger to the stop, not the car

Charging is a rate multiplied by a duration. A site that holds a car for four hours does not need a fast point - it needs one that quietly delivers a useful charge across those four hours. A site where people stop for forty minutes needs something quite different.

So the useful question is: how long does a vehicle sit at your site on a typical day? Answer that honestly and the charger picks itself.

If vehicles stay The unit that fits Why
Scooters and bikes, cycling through ChargeSpot 3.3 The cheapest point per bay. Built for two-wheeler and delivery-fleet parking.
Overnight, residential ChargeSpot 3.6 Long window, gentle on a building's sanctioned load.
Three to five hours ChargeSpot 7 Retail, F&B and workplaces. Covers a long visit comfortably.
Around two hours ChargeSpot 11 Malls and offices, where the window is real but not generous.
Under ninety minutes ChargeSpot 22 Highway stops. The most you can usefully deliver in a short stay.

Where people get this wrong

Over-specifying. A housing society that installs 22 kW points for overnight charging has bought speed nobody is awake to use. That money would have gone further as more 3.6 kW bays.

Forgetting the vehicle's own limit. This is the one that surprises people most. The charge rate is set by the lower of the charge point and the car's on-board charger. Plenty of cars on Indian roads accept considerably less than a 22 kW point can offer. Installing 22 kW does not make those cars charge at 22 kW.

Counting the bay instead of the day. One bay used six times a day does more work than three bays used once each. Before adding connectors, ask whether the ones planned will actually turn over.

Check the supply before you fall in love with a number

The 3.3, 3.6 and 7 kW units run on single phase. The 11 and 22 kW units need three phase.

That single line decides more installations than anything else. It is worth checking what you have at the board before choosing a model, because the answer sometimes settles the question on its own.